The City of Prince George will be doing eight new paving projects over the next week.
They are:
- Bird Street from Queensway to the end of the street (0.30 lane kilometres)
- Foothills Boulevard from Vellencher Road to Highland Drive (1.760 lane kilometres)
- Hamilton Avenue from Queensway to Hazelton Street (Length – 0.410 lane kilometres)
- Highway 16 Frontage from Westgate Road to Marleau Road and Marleau Road to Lalonde Road (1.78 lane kilometres)
- LaSalle Avenue from Queensway to the end of Hazelton Street (0.890 lane kilometres)
- Quadrant Crescent from Queensway to the end of Inlander Street (1.100 lane kilometres)
- Rose Lane from Quadrant Crescent to Regents Crescent (0.390 lane kilometres)
- Royal Crescent from Queensway to Regents Crescent (0.790 lane kilometres)
The City says the projects are scheduled to be completed by September 19th.