Despite lingering protests against it, the Site C project hit another milestone today.

BC Hydro has awarded German firm Voith the $470 million contract for the manufacturer and installation of six turbines and generators.

“The design and manufacture of these units is highly highly specialized work.” BC Hydro CEO Jessica McDonald said “There is only a limited number of companies internationally that are capable of supplying turbines and generators, they have to be custom designed for each hydroelectric facility.”

The supplier has a long history of supplying BC Hydro with turbines and generators dating back to 1930, for projects including: Revelstoke Unit 5 Project, Ruskin Dam and Powerhouse Upgrade, and the Gordon M. Shrum Turbine Replacement Project.

“Site C is currently the biggest energy infrastructure project in Canada. We are proud to bring new power generation capacity to this province.” Voith Canada CEO Bill Malus said

BC Hydro says the turbine-generator units are so large, the fuselage of a Boeing 747 could fit through the penstock. Each turbine-generator unit has an output of 250,000 horsepower, which is equivalent to about 600 Ford Mustang GTs at maximum power.

The turbine-generator section of the project will employ 150 workers at peak installation in 2022.

Something going on in the Prince George area you think people should know about?
Send us a news tip by emailing pgnews@vistaradio.ca.

Continue Reading

cjci Now playing play

cirx Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

PG Mounties say school zone speed watch campaign shows drivers not getting the message

Students returned to school last month and so did school zone speed limits, but according to the Prince George RCMP, many drivers are not remembering to slow down in school zones. 

Carrier Lumber under the microscope: Forest Practices Board to begin regional audit

Operations being audited are within approximately 100 kilometres of Prince George, extending from Bear Lake in the north to Penny in the east, Hixon in the south and the Stuart River to the west. The licence has an allowable annual cut of approximately 187,000 cubic metres.

Hartley’s Cat Scan with Jim Playfair – October 13th, 2026

This is a weekly podcast featuring the ‘who’s who’ of the Prince George Cougars. Hartley’s guest this week is Cougars Associate Coach Jim Playfair.

Eby defends family’s use of $10-a-day childcare program

B.C. NDP Leader David Eby is facing criticism after confirming his family benefited from a $10-a-day child care program his government froze to new providers.

Spruce Kings winless in two-game BCHL Showcase

The Prince George Spruce Kings came out empty handed at the BCHL Showcase in Nisku, Alberta, after a 4-1 loss to the Salmon Arm Silverbacks yesterday (Monday).
- Advertisement -