$200,000 is being added to $300,000 Downtown Renewable Energy project

The Ramada Hotel in Prince George is looking to hook up to the Downtown Renewable Energy System, but that cost just jumped.

Preliminary costs for the project were expected to be around $300,000 in a City Council meeting back in October, but Monday’s meeting reported current labour and material costs bumped the job up to $500,000.

The money will be coming from the Northern Capital Planning Reserve Fund.

Only one bid was put out on the project when it went up for tender.

Manager of Utilities William Wedel explained the installation process.

“So we pay for an installation that goes to an energy transfer station which sits inside of the building, so that’s kind of like the heating system. And from that point further on into the system, that is the responsibility of the property owner.”

He added that the connection comes from the street, and goes into the building, where a unit is put in place, and has a circulation pump attached.

Councillor Brian Skakun asked if this was an attractive price range for potential customers.

“At this point the property owner is still very interested in being connected to it. It’s one of those things like buying an electric car. You don’t necessarily buy it just because it’s the best car, it is because you are doing something for the environment, and also it does provide a good service in the end,” said Wedel.

The City will see the $500,000 come back through delivery charges, but that won’t be for another 12 years.

Wedel noted that the system, once installed, could be a good deal if businesses were planning to expand their building.

“The heat exchanger can be exchanged, and a larger one can be put in place. That unit is relatively inexpensive in comparison to upsizing a boiler system. Boiler systems are 500-600, up to $1 million depending on how complex they are.”

The City also gets greenhouse gas credits for providing more buildings through the Downtown Renewable Energy System.

Skakun noted that he wasn’t happy about the cost increase, but adding more people to the Downtown Renewable Energy System will benefit the City in the long run.

Councillor Garth Frizzell said he was disturbed by the fact that this was the second project where they only received one bid, and Wedel explained that it’s hard to get people to come in for such a small project.

Something going on in the Prince George area you think people should know about?
Send us a news tip by emailing [email protected].

Continue Reading

cjci Now playing play

cirx Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Kodiaks opening season at home Saturday

The Prince George Kodiaks will be taking the field at Masich Place Stadium for their home opener Saturday as the Westshore Rebels come to town.  The Kodiaks are looking to take the next step this season, after a 3-7 finish to the 2024 campaign. 

“It’s kind of been a logistical nightmare” Local CUPW 812 President on Canada Post vote

Canada Post's final offers for employees represented by CUPW has garnered a negative reaction from the union and its members.

Cabinet shuffle “an opportunity for Eby to change the channel”: Bond

Longtime MLA and Political Analyst Shirley Bond was a bit surprised by Premier David Eby's cabinet shuffle today. (Thursday) The shuffle comes just eight months after Eby's cabinet was revealed following the NDP's win in the 2024 provincial election.

Eby shuffles cabinet, including key jobs, public safety and housing roles

Premier David Eby shuffled his cabinet Thursday in what he called a “strategic” move to respond to a world that has changed since his B.C. NDP were elected last fall.

Spruce Kings to play 25 home games on weekends; BCHL has new playoff format

The BCHL has released its the 2025-2026 Regular Season schedule, along with a new divisional alignment playoff format. Each team will play 54 games, starting on Friday, September 19 and running to March 29.
- Advertisement -