Work is continuing to progress on renovations at the Aquatic Centre.
At last night’s (Wednesday) meeting, City Council was presented a report with an update on the renovations.
Some of the work done since the previous quarterly updated presented to Council includes:
Interior Demolition:
- Floor/wall prep for change rooms, washrooms, etc.
- Removal of epoxy flooring and prep for new floor finishes
- Water feature demolition in leisure pool
- Natatorium sound baffle removal
Exterior Demolition:
- Removal and scraping of all peel and stick membranes
- EIFS removal
- Roofing demolition and deck repair
- Roof vapour barrier install (partial)
Mock ups:
- Paint mock up in natatorium, change room and restrooms,
- Vapour barrier – walls
Mechanical and electrical:
- Mechanical room – air handler demolition
- Removal of underwater pool lights
- Removal of valence
- Incoming water service demolition
Upcoming work includes:
- Detailed grout removal in competition pool
- Concrete reinstatement at structural columns
- Roofing demo
- Incoming water service replacement
- Continued electrical and mechanical demolition
- Continued scaffolding and shrink wrap installation
- Continued water feature demolition
- Steel stud removal ongoing.
The full report can be found here.
The total budget for the project is $37 million. City Council approved the project in April 2024. Work started in the fall of 2025, and the pool closed on January 1, 2026.