Prince George City Council was presented a six-month update on significant capital projects during Monday’s City Council meeting.
The report presented showed the City’s capital budget and performance for significant projects over $1 million, indicating total capital expenditures are below the total approved budget allocation.
It includes status information on major, debt and endowment-funded initiatives and covers active works for capital projects.
54 projects were listed, along with notable projects either completed or underway this year, including:
- Aquatic Centre renovation
- Demolition of the former Knights Inn
- Elksentre refrigeration upgrades
- Two Rivers Art Gallery HVAC renewal
- Southridge Watermain replacement
- Library skylight renewal
The City added six projects are listed as under budget, with three listed as under review and the remainder are on plan, and seven listed as behind schedule.
The report aims to keep council and the public informed regarding municipal spending.
During the meeting, council asked administration to return a report after reviewing current and future needs for cremation in the community.
The report is expected to be returned by mid-2027.