Pandemic pushes Site C Dam behind schedule, costs to increase

In a letter addressed to the British Columbia Utilities Commission, David Morton, the President and Chief Executive Officer of BC Hydro, Chris O’Riley released further information regarding BC Hydro’s Site C’s Project.

The project located near Fort St. John, was expected to create 35,000 jobs during the building process, along with an extra 10,000 direct construction jobs and when completed, it will be capable of serving 450,000 homes annually for 100 years.

In O’Riley’s most recent quarterly and annual report, he acknowledged some of the obstacles that caused the delay in the project include: amendments to the main civil works contract, increased costs associated with reservoir clearing, transmission line construction and highway realignment work, additional labour resource requirements, First Nations treaty infringement claims and an injunction application.

He added, “On March 18, 2020, BC Hydro announced it was substantially reducing certain work activities on the project in response to the increasing escalation of provincial measures to manage the COVID-19 pandemic.”

Prior to the escalation of the COVID-19 pandemic, the project remained on schedule for the first generating unit to go into service in late 2023 and a final in-service date in 2024.

O’Riley noted serious concerns in his letter to Morton.

“BC Hydro begun the process to re-baseline the project to determine the impact the COVID-19 pandemic has had on the project’s schedule and budget. It will continue to work with the independent Site C Technical Advisory Board and the Project Assurance Board to determine the appropriate enhancement measures.”

The estimated cost and schedule impacts will be better understood once the enhancement measures are selected.

Something going on in the Prince George area you think people should know about?
Send us a news tip by emailing [email protected].

Continue Reading

cjci Now playing play

cirx Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Hartley’s Sports Shorts; Friday, August 22nd

UNBC Timberwolves:It is the opening weekend of the season for the UNBC Timberwolves in Canada West soccer.The Timberwolves host Thompson Rivers of Kamloops in doubleheaders at Masich Place Stadium.

First Nations call for longer closure of B.C.’s Joffre Lakes park

Two First Nations say British Columbia’s one-month closure of Joffre Lakes Provincial Park to allow for cultural practices is too short and is “a violation of trust.”

B.C. drops to 2-3 in men’s softball at Canada Summer Games

B.C. falls to 2-3 in round robin play. A trio of games await them tomorrow as they take on Saskatchewan (2-2), Quebec (5-0) and Ontario (4-2).

UNBC Computer Science Assistant Professor gets grant for A.I. cybersecurity project

UNBC Computer Science Assistant Professor Dr. Sajal Saha received a Natural Sciences and Engineering Research Council of Canada Discovery Grant.

Lheidli Classic basketball tournament seeing healthy growth heading into second year

"We are starting to pick up momentum over the last couple of weeks having a lot of interest. Last year, we ended up with 11 teams in the men's division last and as it sits today we are close to 20 teams for both the men's and ladies divisions."
- Advertisement -