Simon Fraser Bridge construction delayed, again

The project was announced in January 2022.

It was supposed to be done in the fall of 2022.

Then it was delayed a full year until September 2023, and then October 2023.

Now, the Ministry of Transportation and Infrastructure has told My PG Now they “estimate that the Simon Fraser Bridge will be open to traffic in early December.”

They provided no update on the project’s $20.5 million budget, which has not changed since it was initially set at the start of construction.

According to the Ministry, 18,000 vehicles cross the bridge every day.

Something going on in the Prince George area you think people should know about?
Send us a news tip by emailing [email protected].

Continue Reading

cjci Now playing play

cirx Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Hartley’s Sports Shorts; Monday, July 14th

Special Olympics BC Summer Games: The 2025 Special Olympics BC Summer Games in Prince George is officially over.

Organizers “extremely pleased” with Special Olympics BC Games

After two days of competition, the 2025 Special Olympics BC Summer Games have come to a close.  The games brought around 900 athletes to the Prince George area to compete in ten different sports on Friday and Saturday.  "With any large, large tournament like this, you're always running with your hair straight back just to get everything ready, and we certainly managed to put everything together," said Co-Chair of the Organizing Committee Lyn Hall. 

American Doctor finding warm reception on bike ride from Prince George to Alaska

An American doctor making a journey between two countries is finding friends along the way.  Dr. Craig Davis set out from Prince George in June, riding his bike to Juneau, Alaska on his Riding for Peace campaign.  His goal is to spread a message of peace, and to ask "how can we do better." 

Garbage truck replacement coming before City Council

Prince George City Council will consider replacing a garbage truck at tomorrow's (Monday) meeting. According to a staff report, one of the City's garbage trucks was in a serious motor vehicle accident on Foothills Boulevard on May 13, 2024, resulting in the unit being written off by ICBC.

Darin’s Sports Shorts; Sunday July 13th

Recap of yesterday's sports.
- Advertisement -